CS FundamentalsModerateProduct-company placement
A team lead says: 'We know this shortcut will hurt later, but we must ship for the demo and will pay it back next sprint.' In Fowler's technical-debt quadrant, what kind of debt is this?
- A. Reckless and deliberate
- B. Prudent and deliberate
- C. Reckless and inadvertent
- D. Prudent and inadvertent
Correct answer: B. Prudent and deliberate
The debt is taken knowingly (deliberate) with an understanding of its cost and a plan to repay (prudent). 'What's layering?' would be reckless and inadvertent; 'now we know how we should have built it' is prudent and inadvertent.
Practise more Software Engineering, Git and Cloud Basics questionsSoftware Engineering, Git and Cloud Basics: notes and key points
More Software Engineering, Git and Cloud Basics questions
- A bank must replace a large legacy system without a risky big-bang cut-over. It puts a routing façade in front of it, moves one capability…
- A service calls three downstream APIs using one shared pool of 200 threads. When one API becomes very slow, all 200 threads end up waiting…
- In STRIDE threat modelling, a user denies having approved a large transfer, and the system cannot prove otherwise. Which threat is this…
- A forum shows user comments, and an attacker posts a comment containing a script tag that runs in other users' browsers. Which is the…
- A popular product page is cached with a fixed 60-second TTL. Every minute, as the entry expires, thousands of requests miss at once and…
- According to the cone of uncertainty (Boehm, McConnell), at the initial-concept stage a project's eventual effort can differ from a…