CS FundamentalsModerateProduct-company placement
According to the cone of uncertainty (Boehm, McConnell), at the initial-concept stage a project's eventual effort can differ from a single-point estimate by roughly what factor?
- A. ±10%
- B. From 0.25× to 4× the estimate
- C. From 0.8× to 1.25× the estimate
- D. Exactly 2× in either direction
Correct answer: B. From 0.25× to 4× the estimate
Early estimates are typically off by a factor of up to 4 either way, and the cone narrows only as requirements and design decisions are made. ±10% and 0.8–1.25× are the kind of ranges seen only late in a project.
Practise more Software Engineering, Git and Cloud Basics questionsSoftware Engineering, Git and Cloud Basics: notes and key points
More Software Engineering, Git and Cloud Basics questions
- A team uses feature toggles. Which kind should normally be deleted soon after the feature is fully launched?
- A flight-control system uses N-version programming: three teams independently write the same module from one specification, and a voter…
- A team adds hundreds of snapshot tests that compare whole rendered pages with stored output. Six months later, which problem is most…
- A coverage-guided fuzzer runs a parser for hours with random mutations of seed inputs, and AddressSanitizer is enabled. What can it find…
- After a production outage a team draws a diagram with the problem at the head and branches for People, Process, Tools, Environment and…
- In a RACI matrix for a release task, which rule is standard?