After a production outage a team draws a diagram with the problem at the head and branches for People, Process, Tools, Environment and Code, listing possible contributing causes under each. Which technique is this?
- A. Ishikawa (fishbone) diagram
- B. Pareto chart
- C. Control chart
- D. Five Whys
Correct answer: A. Ishikawa (fishbone) diagram
A fishbone diagram groups candidate causes into categories along branches of a spine leading to the effect. A Pareto chart ranks causes by frequency, and Five Whys drills down one causal chain by repeated questioning.
Practise more Software Engineering, Git and Cloud Basics questionsSoftware Engineering, Git and Cloud Basics: notes and key points
More Software Engineering, Git and Cloud Basics questions
- In a RACI matrix for a release task, which rule is standard?
- COCOMO II computes Effort = 2.94 × Size^E × EAF person-months, with E = 0.91 + 0.01 × (sum of scale factors). For a 40 KSLOC project with…
- A project is behind schedule. The manager can either add people to critical-path activities or start some critical activities in parallel…
- Critical chain project management removes the safety margin from each task estimate and pools it into a project buffer at the end. Which…
- A rules engine must evaluate business rules such as (age > 18 AND country = 'IN') OR isVip from a small fixed grammar, using one class per…
- Match each module with its type of cohesion. P: computes the mean, maximum and histogram of the same input array. Q: performs one of…