CS FundamentalsVery hardGATE CS
COCOMO II computes Effort = 2.94 × Size^E × EAF person-months, with E = 0.91 + 0.01 × (sum of scale factors). For a 40 KSLOC project with scale factors summing to 19 and EAF = 1.2, what is the estimated effort?
- A. About 204 person-months
- B. About 170 person-months
- C. About 101 person-months
- D. About 141 person-months
Correct answer: A. About 204 person-months
E = 0.91 + 0.19 = 1.10 and 40^1.10 ≈ 57.8, so 2.94 × 57.8 × 1.2 ≈ 204 PM. 170 forgets EAF, 101 forgets the scale factors (E = 0.91), and 141 uses E = 1.
Practise more Software Engineering, Git and Cloud Basics questionsSoftware Engineering, Git and Cloud Basics: notes and key points
More Software Engineering, Git and Cloud Basics questions
- A project is behind schedule. The manager can either add people to critical-path activities or start some critical activities in parallel…
- Critical chain project management removes the safety margin from each task estimate and pools it into a project buffer at the end. Which…
- A rules engine must evaluate business rules such as (age > 18 AND country = 'IN') OR isVip from a small fixed grammar, using one class per…
- Match each module with its type of cohesion. P: computes the mean, maximum and histogram of the same input array. Q: performs one of…
- A media player has states Stopped, Playing and Paused and events play, pause and stop. Valid transitions: Stopped–play→Playing…
- A UML class diagram says each Course has 1..3 Instructors and each Instructor teaches 0..4 Courses (many-to-many). Which configuration is…