A project is behind schedule. The manager can either add people to critical-path activities or start some critical activities in parallel that were planned in sequence. Which statement is correct?
- A. Both are called crashing, and both mainly increase risk without increasing cost
- B. Fast-tracking adds resources, while crashing overlaps activities
- C. Both shorten the project even if applied to non-critical activities
- D. Adding resources is crashing, which usually raises cost; overlapping activities is fast-tracking, which mainly raises the risk of rework
Correct answer: D. Adding resources is crashing, which usually raises cost; overlapping activities is fast-tracking, which mainly raises the risk of rework
Crashing buys time with extra resources (cost goes up, ideally on the cheapest critical activity); fast-tracking overlaps dependent work, saving time but risking rework. Shortening non-critical activities does not shorten the project.
Practise more Software Engineering, Git and Cloud Basics questionsSoftware Engineering, Git and Cloud Basics: notes and key points
More Software Engineering, Git and Cloud Basics questions
- Critical chain project management removes the safety margin from each task estimate and pools it into a project buffer at the end. Which…
- A rules engine must evaluate business rules such as (age > 18 AND country = 'IN') OR isVip from a small fixed grammar, using one class per…
- Match each module with its type of cohesion. P: computes the mean, maximum and histogram of the same input array. Q: performs one of…
- A media player has states Stopped, Playing and Paused and events play, pause and stop. Valid transitions: Stopped–play→Playing…
- A UML class diagram says each Course has 1..3 Instructors and each Instructor teaches 0..4 Courses (many-to-many). Which configuration is…
- A company split its monolith into 12 microservices, but every release still needs all 12 deployed together in a fixed order, and several…