CS FundamentalsHardMBA placement · Product-company placement

A project is behind schedule. The manager can either add people to critical-path activities or start some critical activities in parallel that were planned in sequence. Which statement is correct?

  1. A. Both are called crashing, and both mainly increase risk without increasing cost
  2. B. Fast-tracking adds resources, while crashing overlaps activities
  3. C. Both shorten the project even if applied to non-critical activities
  4. D. Adding resources is crashing, which usually raises cost; overlapping activities is fast-tracking, which mainly raises the risk of rework

Correct answer: D. Adding resources is crashing, which usually raises cost; overlapping activities is fast-tracking, which mainly raises the risk of rework

Crashing buys time with extra resources (cost goes up, ideally on the cheapest critical activity); fast-tracking overlaps dependent work, saving time but risking rework. Shortening non-critical activities does not shorten the project.