A release burndown has stayed almost flat for three sprints, yet the team's velocity has been a steady 30 points per sprint. Which chart makes the cause visible, and what is it likely to show?

  1. A. A cumulative flow diagram showing too few items in progress at once across the board
  2. B. A burn-up chart with done work rising 30 per sprint and total scope rising about as fast
  3. C. A burn-up chart with done work flat, proving that velocity has been measured wrongly
  4. D. A sprint burndown showing that every story in each sprint was finished on its last day

Correct answer: B. A burn-up chart with done work rising 30 per sprint and total scope rising about as fast

A net burndown mixes progress and scope change. A burn-up plots completed work and total scope separately, so steady delivery matched by about 30 points of new scope each sprint shows clearly.