CS FundamentalsHardService-company placement · Agile
A release burndown has stayed almost flat for three sprints, yet the team's velocity has been a steady 30 points per sprint. Which chart makes the cause visible, and what is it likely to show?
- A. A cumulative flow diagram showing too few items in progress at once across the board
- B. A burn-up chart with done work rising 30 per sprint and total scope rising about as fast
- C. A burn-up chart with done work flat, proving that velocity has been measured wrongly
- D. A sprint burndown showing that every story in each sprint was finished on its last day
Correct answer: B. A burn-up chart with done work rising 30 per sprint and total scope rising about as fast
A net burndown mixes progress and scope change. A burn-up plots completed work and total scope separately, so steady delivery matched by about 30 points of new scope each sprint shows clearly.
Practise more Software Engineering, Git and Cloud Basics questionsSoftware Engineering, Git and Cloud Basics: notes and key points
More Software Engineering, Git and Cloud Basics questions
- A work item spent 4 days waiting for development, 2 days in development, 5 days waiting for review, 0.5 day in review, 3 days waiting for…
- How many of these statements about Git submodules are correct? 1. A plain git clone of the superproject leaves submodule directories empty…
- On main you run git merge -s ours feature in one repository and git merge -X ours feature in a copy. Which statement is correct?
- main and feature split at commit B. Since then main has gained commit C (editing a.txt) and feature has gained commit D (editing b.txt)…
- main has A-B-C. feature branched from B and has D-E. On main you run git merge feature, creating merge commit M (first parent C, second…
- Which practice is characteristic of the Cleanroom software engineering process?