A work item spent 4 days waiting for development, 2 days in development, 5 days waiting for review, 0.5 day in review, 3 days waiting for testing and 0.5 day in testing. What is its flow efficiency?

  1. A. 25%
  2. B. 80%
  3. C. 20%
  4. D. 33%

Correct answer: C. 20%

Active time is 2 + 0.5 + 0.5 = 3 days and lead time is 4 + 2 + 5 + 0.5 + 3 + 0.5 = 15 days, so 3/15 = 20%. 25% divides by the 12 waiting days, and 80% is the share of time spent waiting.