A work item spent 4 days waiting for development, 2 days in development, 5 days waiting for review, 0.5 day in review, 3 days waiting for testing and 0.5 day in testing. What is its flow efficiency?
- A. 25%
- B. 80%
- C. 20%
- D. 33%
Correct answer: C. 20%
Active time is 2 + 0.5 + 0.5 = 3 days and lead time is 4 + 2 + 5 + 0.5 + 3 + 0.5 = 15 days, so 3/15 = 20%. 25% divides by the 12 waiting days, and 80% is the share of time spent waiting.
Practise more Software Engineering, Git and Cloud Basics questionsSoftware Engineering, Git and Cloud Basics: notes and key points
More Software Engineering, Git and Cloud Basics questions
- How many of these statements about Git submodules are correct? 1. A plain git clone of the superproject leaves submodule directories empty…
- On main you run git merge -s ours feature in one repository and git merge -X ours feature in a copy. Which statement is correct?
- main and feature split at commit B. Since then main has gained commit C (editing a.txt) and feature has gained commit D (editing b.txt)…
- main has A-B-C. feature branched from B and has D-E. On main you run git merge feature, creating merge commit M (first parent C, second…
- Which practice is characteristic of the Cleanroom software engineering process?
- A project has budget at completion ₹900 lakh, earned value ₹360 lakh and actual cost ₹420 lakh. What is the to-complete performance index…