A project has budget at completion ₹900 lakh, earned value ₹360 lakh and actual cost ₹420 lakh. What is the to-complete performance index (TCPI) needed to finish on the original budget?
- A. 0.857
- B. 1.167
- C. 1.125
- D. 0.889
Correct answer: C. 1.125
TCPI = (BAC − EV) / (BAC − AC) = 540 / 480 = 1.125: every remaining rupee must earn ₹1.125 of value. 0.857 is the current CPI (360/420), and 1.167 is its reciprocal.
Practise more Software Engineering, Git and Cloud Basics questionsSoftware Engineering, Git and Cloud Basics: notes and key points
More Software Engineering, Git and Cloud Basics questions
- The Jelinski–Moranda model says the failure intensity before the i-th failure is φ(N − i + 1), where N is the initial number of faults and…
- In McCall's quality model, factors are grouped under product operation, product revision and product transition. Match each factor with…
- A loop while i < n: i = i + 1 (integers) has the invariant i ≤ n. To prove TOTAL correctness rather than only partial correctness, what…
- Match each UML sequence-diagram combined fragment with its meaning. P. alt Q. opt R. loop S. par 1. Runs only if its single guard is true…
- In a UML component diagram, PaymentService shows a small circle on a stick labelled IPayment, and Checkout shows a half-circle cup…
- A team uses Basic COCOMO for a 50 KLOC project. How many times larger is the embedded-mode effort (3.6 × KLOC^1.20) than the organic-mode…