The Jelinski–Moranda model says the failure intensity before the i-th failure is φ(N − i + 1), where N is the initial number of faults and each fault is fixed perfectly once found. With N = 50 and φ = 0.01 per hour, 20 failures have been seen and fixed. What is the expected time to the next failure?
- A. About 3.45 hours
- B. 2 hours
- C. About 3.33 hours
- D. About 5 hours
Correct answer: C. About 3.33 hours
The next failure is the 21st, so λ = 0.01 × (50 − 21 + 1) = 0.30 per hour and the mean time to it is 1/0.30 ≈ 3.33 h. Using N − i = 29 gives 3.45 h, and 2 h uses the initial intensity 0.5 per hour.
Practise more Software Engineering, Git and Cloud Basics questionsSoftware Engineering, Git and Cloud Basics: notes and key points
More Software Engineering, Git and Cloud Basics questions
- In McCall's quality model, factors are grouped under product operation, product revision and product transition. Match each factor with…
- A loop while i < n: i = i + 1 (integers) has the invariant i ≤ n. To prove TOTAL correctness rather than only partial correctness, what…
- Match each UML sequence-diagram combined fragment with its meaning. P. alt Q. opt R. loop S. par 1. Runs only if its single guard is true…
- In a UML component diagram, PaymentService shows a small circle on a stick labelled IPayment, and Checkout shows a half-circle cup…
- A team uses Basic COCOMO for a 50 KLOC project. How many times larger is the embedded-mode effort (3.6 × KLOC^1.20) than the organic-mode…
- A work breakdown structure is said to follow the 100% rule. What does that mean?