A work breakdown structure is said to follow the 100% rule. What does that mean?

  1. A. Each work package must be estimated with full confidence before any work on it starts
  2. B. Every task must be assigned to one person who is allocated to it for 100% of their time
  3. C. Each element's children cover all of its work and nothing outside its scope
  4. D. The project must use its whole budget before any change request can be accepted

Correct answer: C. Each element's children cover all of its work and nothing outside its scope

The 100% rule says the WBS captures all the work in scope, including management work, with every level summing exactly to its parent, so nothing is missed and nothing extra is added.