A work breakdown structure is said to follow the 100% rule. What does that mean?
- A. Each work package must be estimated with full confidence before any work on it starts
- B. Every task must be assigned to one person who is allocated to it for 100% of their time
- C. Each element's children cover all of its work and nothing outside its scope
- D. The project must use its whole budget before any change request can be accepted
Correct answer: C. Each element's children cover all of its work and nothing outside its scope
The 100% rule says the WBS captures all the work in scope, including management work, with every level summing exactly to its parent, so nothing is missed and nothing extra is added.
Practise more Software Engineering, Git and Cloud Basics questionsSoftware Engineering, Git and Cloud Basics: notes and key points
More Software Engineering, Git and Cloud Basics questions
- A game studio adds Git LFS for its .psd and .fbx files. Which statement is correct?
- A developer uses git worktree add ../hotfix main while her current directory has feature checked out. Which statement is correct?
- A Scrum team keeps pulling stories into sprints that lack acceptance criteria and depend on undecided UX. Which agreement addresses this…
- In a speech-recognition system, independent knowledge sources (acoustic, lexical, syntactic) each read and update a shared store of…
- IFPUG rates an external input by file types referenced (FTR) and data element types (DET): with 0–1 FTR it is low up to 15 DETs and…
- A static analyser marks request parameters as untrusted, follows them through assignments and calls, and warns when one reaches a SQL…