CS FundamentalsVery hardService-company placement · GATE CS
A team uses Basic COCOMO for a 50 KLOC project. How many times larger is the embedded-mode effort (3.6 × KLOC^1.20) than the organic-mode effort (2.4 × KLOC^1.05)?
- A. About 1.5 times
- B. About 2.7 times
- C. About 1.8 times
- D. About 3.4 times
Correct answer: B. About 2.7 times
The ratio is (3.6/2.4) × 50^(1.20 − 1.05) = 1.5 × 50^0.15 ≈ 1.5 × 1.80 ≈ 2.7 (about 394 vs 146 person-months). 1.5 compares only the coefficients, and 1.8 only the size factor.
Practise more Software Engineering, Git and Cloud Basics questionsSoftware Engineering, Git and Cloud Basics: notes and key points
More Software Engineering, Git and Cloud Basics questions
- A work breakdown structure is said to follow the 100% rule. What does that mean?
- A game studio adds Git LFS for its .psd and .fbx files. Which statement is correct?
- A developer uses git worktree add ../hotfix main while her current directory has feature checked out. Which statement is correct?
- A Scrum team keeps pulling stories into sprints that lack acceptance criteria and depend on undecided UX. Which agreement addresses this…
- In a speech-recognition system, independent knowledge sources (acoustic, lexical, syntactic) each read and update a shared store of…
- IFPUG rates an external input by file types referenced (FTR) and data element types (DET): with 0–1 FTR it is low up to 15 DETs and…