A product manager ranks 8 candidate requirements with the Analytic Hierarchy Process, comparing every pair once. How many pairwise comparisons are needed, and what happens to the count if 4 more requirements are added?
- A. 28; it rises to 66
- B. 64; it rises to 144
- C. 28; it rises to 42
- D. 56; it rises to 132
Correct answer: A. 28; it rises to 66
AHP needs n(n − 1)/2 comparisons: 8 × 7 / 2 = 28, and for 12 it is 12 × 11 / 2 = 66. The quadratic growth is why AHP is used only for short lists. 56 counts each pair in both orders.
Practise more Software Engineering, Git and Cloud Basics questionsSoftware Engineering, Git and Cloud Basics: notes and key points
More Software Engineering, Git and Cloud Basics questions
- A team can (A) build a module in-house: 60% chance of gaining ₹50 lakh and 40% chance of losing ₹20 lakh; (B) buy a licence for a certain…
- Usability studies model the share of problems found by n test users as 1 − (1 − L)ⁿ, where L is the probability that one user reveals a…
- Which feature characterises the RAD (Rapid Application Development) model?
- The suite { classify([]), classify([1, -2]) } runs against the function below. Treating each if, the for loop (enter / skip-or-exit) and…
- A program classifies three side lengths as equilateral, isosceles, scalene or 'not a triangle' (when the two shorter sides sum to no more…
- A class has fields a, b, c, d and methods m1 (uses a, b), m2 (uses b), m3 (uses c), m4 (uses c, d) and m5 (uses no field but calls m1)…