Why do many agile teams estimate story points on a Fibonacci-like scale (1, 2, 3, 5, 8, 13, …) instead of 1 to 10?

  1. A. Uncertainty grows with size, so wider gaps avoid false precision on big items
  2. B. Fibonacci numbers add up to whole sprints more easily, which simplifies capacity plans
  3. C. Velocity in Fibonacci points converts directly into hours by a fixed formula
  4. D. The Scrum Guide prescribes this scale for every product backlog item

Correct answer: A. Uncertainty grows with size, so wider gaps avoid false precision on big items

Relative estimates of large items are rough, so the scale offers fewer, wider choices as size grows (is it 8 or 13?, not 11 or 12). Points are not hours, and the Scrum Guide says nothing about estimation scales.