An activity not on the critical path has a total float of 3 days and a free float of 1 day. It is delayed by 5 days, and nothing else changes. What is the effect?
- A. The project finishes 2 days late, and its successor activities start later
- B. The project is not delayed, because the activity is non-critical
- C. The project finishes 4 days late, because only the free float absorbs delay
- D. The project finishes 5 days late, because any delay passes to the end date
Correct answer: A. The project finishes 2 days late, and its successor activities start later
Total float is how much the activity can slip without moving the end date, so 5 − 3 = 2 days late. Free float (1 day) only protects the next activity's earliest start, so successors are pushed back too.
Practise more Software Engineering, Git and Cloud Basics questionsSoftware Engineering, Git and Cloud Basics: notes and key points
More Software Engineering, Git and Cloud Basics questions
- Which loop invariant lets you prove this binary search correct for a sorted list a? python lo, hi = 0, len(a) - 1 while lo <= hi: mid =…
- A team has 40 open defects; 15 new ones arrive and 25 are fixed each week. If these rates hold, how long until the backlog is cleared?
- Which statement correctly contrasts a centralised VCS such as Subversion with Git?
- Two artists keep overwriting each other's edits to the same layered .psd file in Git. Why does the usual merge workflow fail, and what…
- Priya rebases Rahul's three commits onto the latest main. What happens to the author and committer fields of the rewritten commits?
- Business rules like 'premium customer AND (order > ₹10,000 OR festive season)' are built as small objects with isSatisfiedBy(candidate)…