An activity not on the critical path has a total float of 3 days and a free float of 1 day. It is delayed by 5 days, and nothing else changes. What is the effect?

  1. A. The project finishes 2 days late, and its successor activities start later
  2. B. The project is not delayed, because the activity is non-critical
  3. C. The project finishes 4 days late, because only the free float absorbs delay
  4. D. The project finishes 5 days late, because any delay passes to the end date

Correct answer: A. The project finishes 2 days late, and its successor activities start later

Total float is how much the activity can slip without moving the end date, so 5 − 3 = 2 days late. Free float (1 day) only protects the next activity's earliest start, so successors are pushed back too.