CS FundamentalsHardGATE CS · Software Engineering · Advanced
Four independent defect-removal activities remove 60%, 50%, 55% and 70% of the defects present when they run (each acts on what the previous ones left behind). What is the cumulative defect removal efficiency of the whole sequence?
- A. 97.30%
- B. 58.75%
- C. 11.55%
- D. 80.00%
Correct answer: A. 97.30%
Defects that survive all four activities: 0.4 x 0.5 x 0.45 x 0.3 = 0.027, so the cumulative efficiency is 97.3%. Averaging the four rates (58.75%) ignores that removals compound.
Practise more Software Engineering, Git and Cloud Basics questionsSoftware Engineering, Git and Cloud Basics: notes and key points
More Software Engineering, Git and Cloud Basics questions
- A project has a budget at completion of 800 units. After some time 60% of the work was planned to be complete, 45% is actually complete…
- The decision (A and B) or (C and D) contains four conditions. What is the minimum number of test cases that achieves 100% modified…
- A routine takes three integer inputs a, b, c, each with a valid range [min, max] with min < max - 1, and one boolean flag f. Under…
- A configuration has 4 parameters with 3 possible values each. What is the minimum number of test cases needed to cover every pair of…
- A team of 6 developers is increased to 9 developers to catch up on a late project. If every pair of team members needs one communication…
- A mutation tool generated 60 mutants. Review shows 10 of them are equivalent mutants, and the current test suite kills 30 of the others…