In Basic COCOMO (organic mode, Effort = 2.4 x (KLOC)^1.05 person-months), what is the approximate effort for a 10 KLOC project?

  1. A. 24.0 person-months
  2. B. 28.8 person-months
  3. C. 26.9 person-months
  4. D. 31.5 person-months

Correct answer: C. 26.9 person-months

10^1.05 is about 11.22, and 2.4 x 11.22 is about 26.9; 24.0 would ignore the 1.05 exponent.