CS FundamentalsHardCapgemini · Infosys
In Basic COCOMO (organic mode, Effort = 2.4 x (KLOC)^1.05 person-months), what is the approximate effort for a 10 KLOC project?
- A. 24.0 person-months
- B. 28.8 person-months
- C. 26.9 person-months
- D. 31.5 person-months
Correct answer: C. 26.9 person-months
10^1.05 is about 11.22, and 2.4 x 11.22 is about 26.9; 24.0 would ignore the 1.05 exponent.
Practise more Software Engineering, Git and Cloud Basics questionsSoftware Engineering, Git and Cloud Basics: notes and key points
More Software Engineering, Git and Cloud Basics questions
- A task has optimistic 4 days, most likely 6 days and pessimistic 14 days. What is the PERT expected duration?
- Which deployment strategy releases a new version to a small subset of users first and widens the rollout gradually while monitoring?
- Why is it advised not to run git rebase on commits already pushed to a shared branch?
- A module of 30,000 lines of code has 45 defects found in testing. What is the defect density?
- Under the cloud shared responsibility model for IaaS (for example virtual machines), which task is the customer's responsibility?
- A Square class extends Rectangle and overrides setWidth so that it also changes the height, breaking code that expects independent width…