CS FundamentalsVery hardWipro NLTH · GATE CS
Module A calls B and C; B calls D and E; C calls F. In top-down integration testing with depth-first ordering, in which order are modules integrated?
- A. A, B, D, E, C, F
- B. A, B, C, D, E, F
- C. D, E, F, B, C, A
- D. A, C, F, B, D, E
Correct answer: A. A, B, D, E, C, F
Depth-first top-down goes down one branch fully (A, B, D, E) before the next (C, F), using stubs for modules not yet integrated.
Practise more Software Engineering, Git and Cloud Basics questionsSoftware Engineering, Git and Cloud Basics: notes and key points
More Software Engineering, Git and Cloud Basics questions
- For a one-month Sprint, the Scrum Guide's maximum time-boxes are 4 hours for the Sprint Review and 3 hours for the Sprint Retrospective…
- A tester re-runs the existing test suite after a developer changes the code, to confirm that previously working features have not broken…
- Which SDLC model completes each phase (requirements, design, coding, testing, deployment) fully before the next one starts, in a strict…
- Which Git command makes a full local copy of a remote repository, including its history?
- In Scrum, who is responsible for ordering (prioritising) the Product Backlog?
- A company uses a web-based email service where the provider runs everything from servers to the application itself. Which cloud service…