CS FundamentalsHardCognizant · Capgemini pattern
How many of the following statements about Scrum are correct? 1. A sprint may be extended by a few days when the sprint goal has not yet been met. 2. The Daily Scrum is time-boxed to 15 minutes. 3. The Sprint Retrospective takes place after the Sprint Review and before the next Sprint Planning. 4. The Scrum Master assigns individual tasks to developers during the sprint.
- A. Only one
- B. Only two
- C. Only three
- D. All four
Correct answer: B. Only two
2 and 3 are correct (Scrum Guide). 1 is wrong: a sprint is a fixed time-box of one month or less and is never extended; unfinished work returns to the Product Backlog. 4 is wrong: developers are self-managing and pick their own work; the Scrum Master coaches and removes impediments. So two are correct.
Practise more Software Engineering, Git and Cloud Basics questionsSoftware Engineering, Git and Cloud Basics: notes and key points
More Software Engineering, Git and Cloud Basics questions
- In top-down integration testing, the top-level module is ready but the lower-level modules it calls are not. What must the testers write…
- Mutation testing creates 50 mutants of a program. 5 of them are equivalent mutants (they behave identically to the original). The test…
- Before release, 120 defects are found in system testing and 30 in user acceptance testing. After release, customers report 50 more. What…
- Arrange these types of module coupling from WORST (tightest) to BEST (loosest).
- What is the cyclomatic complexity of this function, counting the conditional expression and the except clause as decisions? python def…
- How many of the following are white-box (structural) testing techniques? 1. Branch (decision) coverage 2. Basis path testing 3. Boundary…