CS FundamentalsHardTCS NQT · Infosys interview pattern
A team commits 40 story points to a 10-day sprint. After day 6, the burndown chart shows 28 points remaining. If work continues at the same average rate, how many points will be left unfinished at the end of the sprint?
- A. 20
- B. 8
- C. 12
- D. 0
Correct answer: A. 20
Burned so far: 40 − 28 = 12 points in 6 days, i.e. 2 points per day. In the remaining 4 days the team will burn 8 more, leaving 28 − 8 = 20 points. 8 is the work that WILL be done, not what remains.
Practise more Software Engineering, Git and Cloud Basics questionsSoftware Engineering, Git and Cloud Basics: notes and key points
More Software Engineering, Git and Cloud Basics questions
- A library following Semantic Versioning is at version 2.4.7. The next release removes a public method that clients may be calling. What…
- A bug exists at the current commit but not at a commit 200 commits earlier. Using git bisect (a binary search through history), what is…
- What distinguishes continuous deployment from continuous delivery?
- In a unit test, the real payment gateway is replaced by an object that records calls so that the test can assert “charge() was called…
- Using a three-point PERT estimate, a task has optimistic time 4 days, most likely 6 days and pessimistic 14 days. What is the expected…
- An application is modified so that it keeps working after the company moves it to a new operating system version and a new database…