A 600 rev/kWh meter, found to register 3% fast, is on a true load of 2 kW. The time it takes for 40 revolutions is

  1. A. 116.5 s
  2. B. 120 s
  3. C. 2 s
  4. D. 123.7 s

Correct answer: A. 116.5 s

Rev rate = K·P·(1+0.03) rev/h = 1236.0/h; t = 40/rate = 116.5 s (nominal 120.0 s).