Mechanical EngineeringHard

A PERT activity has optimistic time 2, most likely time 5 and pessimistic time 14. Its expected time is

  1. A. 5
  2. B. 6
  3. C. 7
  4. D. 8

Correct answer: B. 6

te = (a + 4m + b)/6 = (2 + 20 + 14)/6 = 6.