Mechanical EngineeringHard
A PERT activity has optimistic time 2, most likely time 5 and pessimistic time 14. Its expected time is
- A. 5
- B. 6
- C. 7
- D. 8
Correct answer: B. 6
te = (a + 4m + b)/6 = (2 + 20 + 14)/6 = 6.