A network has activity A (3 days) followed by two parallel activities B (5 days) and C (9 days), both followed by D (3 days). The minimum project duration is

  1. A. 15 days
  2. B. 9 days
  3. C. 20 days
  4. D. 11 days

Correct answer: A. 15 days

Paths: A-B-D = 11, A-C-D = 15; critical path = 15 days; float of B = 4 days.