Budgeted fixed overhead is ₹1,20,000 for 12,000 units (₹10 a unit). Actual output is 11,000 units and actual fixed overhead ₹1,26,000. What is the fixed overhead volume variance?

  1. A. ₹6,000 (A)
  2. B. ₹16,000 (A)
  3. C. ₹10,000 (F)
  4. D. ₹10,000 (A)

Correct answer: D. ₹10,000 (A)

Volume variance = rate × (actual output − budgeted output) = 10 × (11,000 − 12,000) = ₹10,000 (A). The ₹6,000 (A) is the expenditure variance; together they make the total ₹16,000 (A).