A standard cost is:
- A. A predetermined cost a unit should incur under efficient working
- B. The actual historical cost recorded for the most recent production batch
- C. The market selling price of the finished product less profit
- D. The average cost incurred by competitors in the same industry
Correct answer: A. A predetermined cost a unit should incur under efficient working
Standards are set in advance; comparing them with actual costs gives the variances used for control.
Practise more Financial & Cost Accounting questionsFinancial & Cost Accounting: notes and key points
More Financial & Cost Accounting questions
- Standard: 2 machine hours per unit and variable overhead of ₹15 an hour. 4,000 units are produced in 8,400 hours, and actual variable…
- In budgeting, the 'principal budget factor' (key factor) is:
- The standard labour rate is ₹50 an hour; 2,000 hours are paid at ₹48 an hour. What is the labour rate variance?
- Goods are sent on consignment by a manufacturer to an agent in another city. Until the agent sells them, who owns the goods?
- 1,000 units costing ₹200 each are sent on consignment. The consignor pays freight of ₹10,000 and the consignee pays unloading and carriage…
- A consignee sells consigned goods for ₹5,00,000: ₹3,00,000 in cash and ₹2,00,000 on credit. He gets 5% ordinary commission and 2% del…