A standard cost is:

  1. A. A predetermined cost a unit should incur under efficient working
  2. B. The actual historical cost recorded for the most recent production batch
  3. C. The market selling price of the finished product less profit
  4. D. The average cost incurred by competitors in the same industry

Correct answer: A. A predetermined cost a unit should incur under efficient working

Standards are set in advance; comparing them with actual costs gives the variances used for control.