Management & CommerceVery hardBig 4 · Bank MT · MBA placement pattern

A fixed-price contract for ₹40 lakh has incurred costs of ₹25 lakh and needs a further ₹20 lakh to complete. It is 25/45 complete. How much loss is recognised this year?

  1. A. ₹5 lakh
  2. B. ₹2.78 lakh
  3. C. Nil
  4. D. ₹25 lakh

Correct answer: A. ₹5 lakh

Total expected cost ₹45 lakh exceeds the price by ₹5 lakh, so the contract is onerous and the entire expected loss is recognised at once, not in proportion to progress. ₹2.78 lakh spreads the loss by completion (25/45).