Standard labour is 4 hours per unit at ₹50 per hour. In a month 2,000 units are made. Workers are paid for 8,400 hours (wages ₹4,41,000), of which 300 hours were idle because of a power failure. What is the labour efficiency variance?

  1. A. ₹5,000 adverse
  2. B. ₹20,000 adverse
  3. C. ₹15,000 adverse
  4. D. ₹21,000 adverse

Correct answer: A. ₹5,000 adverse

Efficiency variance is measured on hours actually worked: (8,000 - 8,100) x 50 = 5,000 adverse. Idle time (300 x 50 = 15,000) and the rate variance (441,000 - 8,400 x 50 = 21,000) are separate; together they total the 41,000 adverse labour cost variance.