Management & CommerceVery hardCFA Level I · MBA placement
A firm has ₹10 crore to invest. Projects are DIVISIBLE: P (cost ₹4 crore, NPV ₹2.0 crore), Q (₹5 crore, ₹1.5 crore), R (₹3 crore, ₹1.2 crore), S (₹2 crore, ₹0.4 crore). What is the maximum total NPV?
- A. ₹3.50 crore
- B. ₹3.60 crore
- C. ₹3.20 crore
- D. ₹4.10 crore
Correct answer: D. ₹4.10 crore
Rank by profitability index: P (1.50), R (1.40), Q (1.30), S (1.20). Take P and R fully (₹7 crore, NPV ₹3.2 crore) and 3/5 of Q (NPV ₹0.9 crore): total ₹4.10 crore. Ranking by absolute NPV (P + Q = ₹3.5 crore) wastes the budget's best uses.
Practise more Corporate Finance & Financial Markets questionsCorporate Finance & Financial Markets: notes and key points
More Corporate Finance & Financial Markets questions
- A ₹12 lakh project lasts 6 years with no salvage value. At an 11% cost of capital, what is the minimum equal annual cash inflow at which…
- An investment costs ₹5 lakh and pays ₹60,000 at the end of year 1, with the payment then growing at 2% a year forever. What is its IRR?
- A ₹100 crore project returns ₹50 crore at the end of year 1. At that point the PV of its remaining cash flows will be either ₹120 crore or…
- A ₹20 lakh asset is depreciated straight-line over 4 years to zero. The tax rate is 25% and the discount rate 10%. What is the present…
- Which statements about a conventional project's NPV profile are correct? I. It cuts the horizontal axis at the IRR. II. Its vertical-axis…
- For a new plant, a firm lists: (a) ₹40 lakh already spent on R&D; (b) a building it owns that could be rented out for ₹12 lakh a year; (c)…