Management & CommerceHardFinance analyst · Bank MT · MBA placement pattern
Assertion (A): IRR can rank two mutually exclusive projects differently from NPV. Reason (R): IRR implicitly assumes intermediate cash flows are reinvested at the project's own IRR, whereas NPV assumes reinvestment at the cost of capital.
- A. Both A and R are true, and R is the correct explanation of A
- B. Both A and R are true, but R is not the correct explanation of A
- C. A is true, but R is false
- D. A is false, but R is true
Correct answer: A. Both A and R are true, and R is the correct explanation of A
Both are true. The different reinvestment-rate assumptions (along with differences in scale and timing) are the standard explanation for NPV–IRR ranking conflicts.
Practise more Corporate Finance & Financial Markets questionsCorporate Finance & Financial Markets: notes and key points
More Corporate Finance & Financial Markets questions
- A ₹10 lakh project yields ₹2.5 lakh a year for 6 years; the cost of capital is 12%. By what percentage can annual inflows fall before the…
- Which statements about payback are correct? I. Simple payback ignores cash flows after the payback date. II. Discounted payback can never…
- A project costing ₹1,60,000 is expected to generate ₹1,00,000 a year for 2 years in TODAY'S prices. The nominal cost of capital is 15.5%…
- Which capital budgeting method ignores the time value of money?
- A diversified firm uses its company-wide WACC of 11% to evaluate all projects. Over time, this practice tends to:
- Match each technique with its feature. Techniques: (p) NPV, (q) IRR, (r) PI, (s) Payback. Features: (1) Best for ranking divisible…