Management & CommerceVery hardHR · cost accounting · MBA placement
Under a Gantt task-and-bonus plan, a worker who finishes a job within the standard time is paid for the full standard time plus a bonus of 25% of that standard-time wage; a worker who takes longer gets ordinary time wages for the hours actually worked. The standard time is 10 hours and the rate is ₹60 an hour. X finishes in 8 hours and Y takes 12 hours. What do they earn?
- A. X ₹750, Y ₹720
- B. X ₹600, Y ₹720
- C. X ₹750, Y ₹600
- D. X ₹600, Y ₹600
Correct answer: A. X ₹750, Y ₹720
X: 10 × ₹60 = ₹600 plus 25% bonus = ₹750. Y keeps the guaranteed time wage: 12 × ₹60 = ₹720. Basing X's pay on the 8 hours actually worked gives ₹600, and denying Y the time-wage guarantee gives ₹600. The near-equal pay shows why Gantt is used to protect learners rather than to reward speed alone.
Practise more HR, Organisational Behaviour & Principles of Management questionsHR, Organisational Behaviour & Principles of Management: notes and key points
More HR, Organisational Behaviour & Principles of Management questions
- A plant needs 2,000 extra labour hours next year. Overtime is paid at double the ordinary rate of ₹200 an hour and attracts no extra…
- Two assessors independently mark 50 group-discussion candidates as Pass or Fail. Both say Pass for 20, both say Fail for 15, A passes and…
- A sales rep earns 5% commission with a recoverable draw of ₹30,000 a month: each month she is paid the higher of the draw and (commission…
- In a promotion cycle, Department A promoted 48 of 80 men and 13 of 20 women; Department B promoted 4 of 20 men and 20 of 80 women…
- A firm of 400 staff has 20% annual attrition and a replacement cost of ₹3 lakh per leaver. A ₹40 lakh retention programme is expected to…
- Assume this rule for registering a trade union of workmen: at least 7 members, and also not less than 10% of the workmen in the…