Management & CommerceVery hardXAT · CAT
The standard time for a job is 10 hours, a worker completes it in 8 hours, and the hourly rate is ₹50. Under the Rowan plan the worker's earnings are
- A. ₹450
- B. ₹500
- C. ₹400
- D. ₹480
Correct answer: D. ₹480
Rowan bonus = (time saved/standard time) × time taken × rate = (2/10) × 8 × 50 = ₹80. Earnings = 400 + 80 = ₹480. The Halsey plan (50% of time saved) would give ₹450.
Practise more HR, Organisational Behaviour & Principles of Management questionsHR, Organisational Behaviour & Principles of Management: notes and key points
More HR, Organisational Behaviour & Principles of Management questions
- Design and production departments at a company pass work back and forth repeatedly in a cycle, each modifying its output on the other's…
- In a point-factor job evaluation, the maximum is 1,000 points, with factor weights of skill 60%, effort 25% and responsibility 15%. A job…
- An employee thinks that effort leads to good performance with probability 0.8. Good performance leads to a bonus (instrumentality 0.5…
- Which of these is NOT one of the core functions of management in the POSDC framework?
- A machine operator gets conflicting instructions from both the production manager and the quality manager every day. Which of Fayol's…
- A factory engineer times each worker's movements with a stopwatch to find the single best way of doing every task and then trains all…