Assertion (A): A Six Sigma process produces about 3.4 defects per million opportunities. Reason (R): Six Sigma improvement projects follow the DMAIC cycle.

  1. A. Both A and R are true, and R is the correct explanation of A
  2. B. Both A and R are true, but R is not the correct explanation of A
  3. C. A is true, but R is false
  4. D. A is false, but R is true

Correct answer: B. Both A and R are true, but R is not the correct explanation of A

Both statements are true, but DMAIC is the project method; it does not explain why six sigma corresponds to 3.4 DPMO. That figure comes from a 4.5σ one-sided tail after allowing a 1.5σ drift of the mean.