Management & CommerceModerateOps MT · Supply chain · MBA placement pattern
Match each acceptance-sampling term with its meaning. 1. AQL 2. LTPD 3. Producer's risk (α) 4. Consumer's risk (β) a. Probability of accepting a lot whose quality is as bad as the LTPD b. Worst average defect level the buyer still regards as satisfactory c. Probability of rejecting a lot whose quality is at the AQL d. Defect level at which the buyer regards a lot as bad
- A. 1-d, 2-b, 3-c, 4-a
- B. 1-b, 2-d, 3-c, 4-a
- C. 1-b, 2-d, 3-a, 4-c
- D. 1-c, 2-a, 3-b, 4-d
Correct answer: B. 1-b, 2-d, 3-c, 4-a
AQL is the acceptable quality level (good lots); LTPD is the lot tolerance percent defective (bad lots). Producer's risk is rejecting a good (AQL) lot; consumer's risk is accepting a bad (LTPD) lot. Swapping the two risks is the classic mistake.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- A sampling plan inspects n = 50 items and accepts the lot if c ≤ 2 defectives are found. Using the Poisson approximation, what is the…
- Over 40 replenishment cycles a store ran out of an item in 5 cycles. Customers asked for 4,500 units in total, of which 4,230 were…
- An item is ordered 500 units at a time. Lead-time demand is normal with σ = 40 units, and the firm holds safety stock of 40 units (z = 1)…
- An importer buys a part at US12 FOB. Take ₹83 per dollar. Freight is ₹40 per unit, insurance is 1% of the FOB value, customs duty is 10%…
- A firm needs 10,000 units of a component a year. A supplier quotes ₹85 per unit. Making it costs, per unit: materials ₹40, direct labour…
- A firm needs 10,000 units of a component a year. A supplier quotes ₹85 per unit. Making it costs, per unit: materials ₹40, direct labour…