Management & CommerceVery hardOps MT · Supply chain · MBA placement pattern

A one-person counter is simulated for six customers. Inter-arrival time: 1 min (RN 00–19), 2 min (20–69), 3 min (70–99). Service time: 1 min (00–29), 2 min (30–69), 3 min (70–99). The clock starts at 0 with the counter empty, and the first customer arrives after the first inter-arrival time. Inter-arrival RNs: 45, 12, 78, 05, 33, 91. Service RNs: 81, 50, 22, 73, 64, 10. What are the total customer waiting time and the counter's idle time until the last customer leaves?

  1. A. Waiting 5 min; idle 2 min
  2. B. Waiting 7 min; idle 0 min
  3. C. Waiting 7 min; idle 2 min
  4. D. Waiting 9 min; idle 3 min

Correct answer: C. Waiting 7 min; idle 2 min

Inter-arrivals 2, 1, 3, 1, 2, 3 → arrivals at 2, 3, 6, 7, 9, 12. Services 3, 2, 1, 3, 2, 1. Starts/ends: C1 2–5; C2 5–7 (waits 2); C3 7–8 (1); C4 8–11 (1); C5 11–13 (2); C6 13–14 (1). Total wait = 7 min. The counter is idle only from 0 to 2, so 2 min, and the last customer leaves at 14.

More Operations, Supply Chain & Business Analytics questions

Exams that ask this topic