Management & CommerceVery hardOps MT · MBA placement
Customers arrive at 8 per hour (Poisson). Option P: two clerks, each serving 5 per hour (exponential), fed from one common queue (M/M/2). Option Q: one clerk who serves 10 per hour (M/M/1). Which statement is correct?
- A. P is better on both queue wait and total time, as pooling always wins
- B. Q is better on both queue wait and total time, as one fast server wins
- C. Both are identical, because total service capacity is 10 per hour
- D. P has the shorter queue wait, but Q the shorter total time in system
Correct answer: D. P has the shorter queue wait, but Q the shorter total time in system
Q: Wq = λ/[μ(μ − λ)] = 24 min and W = 1/(μ − λ) = 30 min. P: P₀ = 1/9, Lq ≈ 2.84, so Wq ≈ 21.3 min, but each service takes 12 min, so W ≈ 33.3 min. Pooling cuts queueing, yet the fast single server wins on total time.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- An emergency department receives 120 patients a day, arriving evenly round the clock. 30% are admitted and spend on average 6 hours in the…
- Requests reach a single server (M/M/1) at 22 per hour. Management wants the average number waiting in the queue, Lq, to be at most 2. What…
- An automated car wash takes exactly 5 minutes per car (constant service time). Cars arrive at random (Poisson) at 9 per hour. What is the…
- A product is forecast with Holt's trend-adjusted exponential smoothing (α = 0.4 for the level, β = 0.3 for the trend). At the end of last…
- An analyst wants a simple exponential-smoothing forecast whose data have the same average age as those of a 9-month simple moving average…
- Annual sales (₹ crore) for years 1 to 5 were 12, 15, 19, 22 and 27. Using a least-squares linear trend, what is the forecast for year 6?