Management & CommerceHardOps MT · MBA placement
An automated car wash takes exactly 5 minutes per car (constant service time). Cars arrive at random (Poisson) at 9 per hour. What is the average time a car waits before its wash starts?
- A. 7.5 minutes
- B. 15 minutes
- C. 12.5 minutes
- D. 3.75 minutes
Correct answer: A. 7.5 minutes
For M/D/1, Lq = ρ²/[2(1 − ρ)] — half the M/M/1 value. ρ = 0.75, so Lq = 1.125 and Wq = 1.125/9 h = 7.5 min. 15 min is the M/M/1 answer; 12.5 min adds the 5-minute wash (time in system).
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- A product is forecast with Holt's trend-adjusted exponential smoothing (α = 0.4 for the level, β = 0.3 for the trend). At the end of last…
- An analyst wants a simple exponential-smoothing forecast whose data have the same average age as those of a 9-month simple moving average…
- Annual sales (₹ crore) for years 1 to 5 were 12, 15, 19, 22 and 27. Using a least-squares linear trend, what is the forecast for year 6?
- Next year's demand is forecast at 4,800 units. The multiplicative seasonal indices for Q1–Q4 are 0.8, 1.1, 1.3 and 0.8. What is the…
- Annual demand is 4,800 units, ordering cost ₹400 per order, holding cost ₹12 per unit per year. Customers accept backorders, and the…
- An item's EOQ is 700 units, but the supplier ships only in pallets of 500 units, so the buyer must order either 500 or 1,000 units. Which…