Management & CommerceHardOps MT · MBA placement
An item's EOQ is 700 units, but the supplier ships only in pallets of 500 units, so the buyer must order either 500 or 1,000 units. Which is cheaper in annual ordering-plus-holding cost, and by roughly how much relative to the EOQ cost?
- A. 500 units; it costs about 5.7% above the EOQ cost versus about 6.4% for 1,000
- B. 1,000 units, because it is closer in ratio terms to the EOQ
- C. Both cost exactly the same because the cost curve is symmetric
- D. 500 units; it costs about 28.6% above the EOQ cost versus about 42.9% for 1,000
Correct answer: A. 500 units; it costs about 5.7% above the EOQ cost versus about 6.4% for 1,000
Cost relative to the EOQ cost is ½(Q/Q* + Q*/Q): for 500 it is ½(0.714 + 1.4) = 1.0571; for 1,000 it is ½(1.429 + 0.7) = 1.0643. The curve is flat and asymmetric, so the 'percentage gap in quantity' (28.6% vs 42.9%) overstates the cost penalty.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- A bakery sells a cake for ₹600 that costs ₹200 to make; unsold cakes are sold next day to a canteen for ₹100. Daily demand is normal with…
- Twenty inspected car bodies show a total of 180 paint blemishes. What are the 3-sigma limits of the c-chart for blemishes per body?
- Samples of 100 tubes are checked each hour; over many samples the average fraction defective is 4%. What is the upper control limit of the…
- A process has Cp = 1.5 and Cpk = 1.0, with a standard deviation of 2 mm. How far is the process mean from the midpoint of the…
- An assembly averages 0.25 defects per unit, and defects occur at random (Poisson). Approximately what fraction of units come through with…
- Which of these patterns on an X̄ control chart signals that the process may be out of control even though every point lies inside the…