Management & CommerceVery hardOps MT · MBA placement
A process has Cp = 1.5 and Cpk = 1.0, with a standard deviation of 2 mm. How far is the process mean from the midpoint of the specification range?
- A. 3 mm
- B. 1.5 mm
- C. 6 mm
- D. 9 mm
Correct answer: A. 3 mm
Cp = (USL − LSL)/6σ = 1.5 gives a half-width of 9 mm. Cpk = (distance to nearer limit)/3σ = 1 gives 6 mm to the nearer limit, so the mean sits 9 − 6 = 3 mm off centre. 6 mm and 9 mm are the two distances themselves.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- An assembly averages 0.25 defects per unit, and defects occur at random (Poisson). Approximately what fraction of units come through with…
- Which of these patterns on an X̄ control chart signals that the process may be out of control even though every point lies inside the…
- Activities (days; immediate predecessors): A 4 (–), B 6 (–), C 3 (A), D 5 (A), E 4 (B, C), F 6 (D), G 2 (E, F). What are the total float…
- A project's critical path has three activities with PERT estimates (optimistic, most likely, pessimistic) in weeks: (3, 5, 9), (2, 4, 12)…
- A project has two parallel paths from start to finish: A (6 days) → B (8 days) → C (5 days), and D (7 days) → E (9 days). Crash cost per…
- Maximise Z = 5x + 4y subject to 6x + 4y ≤ 24 (machine hours), x + 2y ≤ 6 (labour hours), x, y ≥ 0. The optimum is Z = 21. What is the…