A project has two parallel paths from start to finish: A (6 days) → B (8 days) → C (5 days), and D (7 days) → E (9 days). Crash cost per day and maximum crash: A ₹2,000 (2 days), B ₹1,500 (3 days), C ₹2,500 (1 day), D ₹1,000 (2 days), E ₹1,200 (2 days). What is the minimum extra cost to finish the project in 15 days?

  1. A. ₹6,500
  2. B. ₹7,500
  3. C. ₹5,500
  4. D. ₹8,000

Correct answer: B. ₹7,500

Path ABC is 19 days, DE 16. Crash B by 3 days (₹4,500) to reach 16, when both paths are critical. The 16th → 15th day needs one day off each path: A (₹2,000) + D (₹1,000) = ₹3,000, total ₹7,500. Forgetting that DE also becomes critical gives ₹6,500.