A project has two parallel paths from start to finish: A (6 days) → B (8 days) → C (5 days), and D (7 days) → E (9 days). Crash cost per day and maximum crash: A ₹2,000 (2 days), B ₹1,500 (3 days), C ₹2,500 (1 day), D ₹1,000 (2 days), E ₹1,200 (2 days). What is the minimum extra cost to finish the project in 15 days?
- A. ₹6,500
- B. ₹7,500
- C. ₹5,500
- D. ₹8,000
Correct answer: B. ₹7,500
Path ABC is 19 days, DE 16. Crash B by 3 days (₹4,500) to reach 16, when both paths are critical. The 16th → 15th day needs one day off each path: A (₹2,000) + D (₹1,000) = ₹3,000, total ₹7,500. Forgetting that DE also becomes critical gives ₹6,500.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- Maximise Z = 5x + 4y subject to 6x + 4y ≤ 24 (machine hours), x + 2y ≤ 6 (labour hours), x, y ≥ 0. The optimum is Z = 21. What is the…
- A maximisation LP has 3 '≤' constraints and 2 decision variables, and it has a finite optimal solution. Which statements are correct? I…
- During the simplex method for a maximisation problem, the entering variable has been chosen, but every entry in its column of the…
- Payoffs (₹ lakh) of three strategies under three demand states with probabilities 0.3, 0.5 and 0.2: X: 50, 30, 10; Y: 80, 20, −20; Z: 20…
- Supplier A provides 60% of a part with a 3% defect rate; supplier B provides the rest with a 5% defect rate. A part picked at random is…
- A sample of 16 checkouts has a mean basket value of ₹520 with a sample standard deviation of ₹80. H0: μ = ₹480. Critical t-values with 15…