A project's critical path has three activities with PERT estimates (optimistic, most likely, pessimistic) in weeks: (3, 5, 9), (2, 4, 12) and (6, 8, 10). What is the probability of finishing within 21 weeks? (Use Φ(1.30) ≈ 0.903, Φ(0.80) ≈ 0.788, Φ(0.63) ≈ 0.736.)

  1. A. About 78.8%
  2. B. About 73.6%
  3. C. About 90.3%
  4. D. About 50%

Correct answer: C. About 90.3%

Expected times are 5.33, 5 and 8, so T = 18.33 weeks; variances are 1, 2.78 and 0.44, so σ = √4.22 ≈ 2.05. z = (21 − 18.33)/2.05 ≈ 1.3, about 90.3%. Adding the activity standard deviations (σ = 3.33) gives z = 0.80, and dividing by the variance 4.22 gives z ≈ 0.63.