Management & CommerceVery hardOps MT · MBA placement
A project's critical path has three activities with PERT estimates (optimistic, most likely, pessimistic) in weeks: (3, 5, 9), (2, 4, 12) and (6, 8, 10). What is the probability of finishing within 21 weeks? (Use Φ(1.30) ≈ 0.903, Φ(0.80) ≈ 0.788, Φ(0.63) ≈ 0.736.)
- A. About 78.8%
- B. About 73.6%
- C. About 90.3%
- D. About 50%
Correct answer: C. About 90.3%
Expected times are 5.33, 5 and 8, so T = 18.33 weeks; variances are 1, 2.78 and 0.44, so σ = √4.22 ≈ 2.05. z = (21 − 18.33)/2.05 ≈ 1.3, about 90.3%. Adding the activity standard deviations (σ = 3.33) gives z = 0.80, and dividing by the variance 4.22 gives z ≈ 0.63.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- A project has two parallel paths from start to finish: A (6 days) → B (8 days) → C (5 days), and D (7 days) → E (9 days). Crash cost per…
- Maximise Z = 5x + 4y subject to 6x + 4y ≤ 24 (machine hours), x + 2y ≤ 6 (labour hours), x, y ≥ 0. The optimum is Z = 21. What is the…
- A maximisation LP has 3 '≤' constraints and 2 decision variables, and it has a finite optimal solution. Which statements are correct? I…
- During the simplex method for a maximisation problem, the entering variable has been chosen, but every entry in its column of the…
- Payoffs (₹ lakh) of three strategies under three demand states with probabilities 0.3, 0.5 and 0.2: X: 50, 30, 10; Y: 80, 20, −20; Z: 20…
- Supplier A provides 60% of a part with a 3% defect rate; supplier B provides the rest with a 5% defect rate. A part picked at random is…