Management & CommerceVery hardOps MT · MBA placement
Activities (days; immediate predecessors): A 4 (–), B 6 (–), C 3 (A), D 5 (A), E 4 (B, C), F 6 (D), G 2 (E, F). What are the total float and the free float of activity B?
- A. Total float 5 days, free float 5 days
- B. Total float 1 day, free float 1 day
- C. Total float 4 days, free float 1 day
- D. Total float 5 days, free float 1 day
Correct answer: D. Total float 5 days, free float 1 day
Critical path A–D–F–G = 17 days. LS(G) = 15, so LF(E) = 15 and LS(E) = 11; LF(B) = 11 gives LS(B) = 5 and total float 5. Free float = ES(E) − EF(B) = 7 − 6 = 1, because C pushes E's earliest start to day 7.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- A project's critical path has three activities with PERT estimates (optimistic, most likely, pessimistic) in weeks: (3, 5, 9), (2, 4, 12)…
- A project has two parallel paths from start to finish: A (6 days) → B (8 days) → C (5 days), and D (7 days) → E (9 days). Crash cost per…
- Maximise Z = 5x + 4y subject to 6x + 4y ≤ 24 (machine hours), x + 2y ≤ 6 (labour hours), x, y ≥ 0. The optimum is Z = 21. What is the…
- A maximisation LP has 3 '≤' constraints and 2 decision variables, and it has a finite optimal solution. Which statements are correct? I…
- During the simplex method for a maximisation problem, the entering variable has been chosen, but every entry in its column of the…
- Payoffs (₹ lakh) of three strategies under three demand states with probabilities 0.3, 0.5 and 0.2: X: 50, 30, 10; Y: 80, 20, −20; Z: 20…