Activities (days; immediate predecessors): A 4 (–), B 6 (–), C 3 (A), D 5 (A), E 4 (B, C), F 6 (D), G 2 (E, F). What are the total float and the free float of activity B?

  1. A. Total float 5 days, free float 5 days
  2. B. Total float 1 day, free float 1 day
  3. C. Total float 4 days, free float 1 day
  4. D. Total float 5 days, free float 1 day

Correct answer: D. Total float 5 days, free float 1 day

Critical path A–D–F–G = 17 days. LS(G) = 15, so LF(E) = 15 and LS(E) = 11; LF(B) = 11 gives LS(B) = 5 and total float 5. Free float = ES(E) − EF(B) = 7 − 6 = 1, because C pushes E's earliest start to day 7.