Management & CommerceEasyOps MT · Supply chain · MBA placement pattern
In the Theory of Constraints, which scheduling method paces the whole plant to the bottleneck, protects it with a time buffer and releases material in step with it?
- A. Economic Order Quantity
- B. Kanban
- C. Drum–Buffer–Rope
- D. Material Requirements Planning
Correct answer: C. Drum–Buffer–Rope
In Drum–Buffer–Rope the bottleneck is the drum that sets the pace, the buffer protects it from upstream disruptions, and the rope ties material release to the drum's rate.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- Planned production time is 480 minutes, of which 60 minutes are lost to breakdowns. The ideal cycle time is 0.5 min/unit. The machine…
- Monthly sales of a product were 120, 135, 150 and 141 units (oldest first). What is the 3-month moving-average forecast for the next month?
- Sales were 200 (Jan), 220 (Feb) and 250 (Mar). Using a weighted moving average with weights 0.5, 0.3 and 0.2, the heaviest weight on the…
- Last period's forecast was 500 units and actual demand was 540 units. With exponential smoothing and α = 0.3, what is the next forecast?
- The forecast for period 1 was 100. Actual demand in periods 1, 2 and 3 was 110, 95 and 120. Using exponential smoothing with α = 0.2, what…
- Actual demand for four weeks was 100, 120, 80 and 150; the forecasts were 110, 110, 100 and 140. What is the MAPE?