In the Theory of Constraints, which scheduling method paces the whole plant to the bottleneck, protects it with a time buffer and releases material in step with it?

  1. A. Economic Order Quantity
  2. B. Kanban
  3. C. Drum–Buffer–Rope
  4. D. Material Requirements Planning

Correct answer: C. Drum–Buffer–Rope

In Drum–Buffer–Rope the bottleneck is the drum that sets the pace, the buffer protects it from upstream disruptions, and the rope ties material release to the drum's rate.