Planned production time is 480 minutes, of which 60 minutes are lost to breakdowns. The ideal cycle time is 0.5 min/unit. The machine produced 700 units, of which 665 were good. What is the OEE?
- A. 72.9%
- B. 79.2%
- C. 83.1%
- D. 69.3%
Correct answer: D. 69.3%
Availability = 420/480 = 0.875. Performance = (700 × 0.5)/420 = 0.8333. Quality = 665/700 = 0.95. OEE = A × P × Q = 69.3% (check: 665 × 0.5 ÷ 480 = 0.6927). 72.9% leaves out quality.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- Monthly sales of a product were 120, 135, 150 and 141 units (oldest first). What is the 3-month moving-average forecast for the next month?
- Sales were 200 (Jan), 220 (Feb) and 250 (Mar). Using a weighted moving average with weights 0.5, 0.3 and 0.2, the heaviest weight on the…
- Last period's forecast was 500 units and actual demand was 540 units. With exponential smoothing and α = 0.3, what is the next forecast?
- The forecast for period 1 was 100. Actual demand in periods 1, 2 and 3 was 110, 95 and 120. Using exponential smoothing with α = 0.2, what…
- Actual demand for four weeks was 100, 120, 80 and 150; the forecasts were 110, 110, 100 and 140. What is the MAPE?
- Forecast errors (actual − forecast) for six months were +5, +8, −3, +7, +6 and +9. Control limits for the tracking signal are ±4. What is…