A press needs a 40-minute setup before each batch and then 2 minutes per unit. It currently runs batches of 100. By what percentage does its hourly capacity rise if the batch size is doubled to 200?
- A. 100%
- B. About 9.1%
- C. About 16.7%
- D. About 4.5%
Correct answer: B. About 9.1%
Capacity = batch ÷ (setup + batch × unit time): 100/240 min = 25/hr, and 200/440 min = 27.27/hr, a rise of about 9.1%. Doubling the batch only spreads the setup more thinly; output cannot exceed 30/hr however big the batch.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- A packaging line has an OEE of 60%. Its availability is 80% and its quality rate is 95%. What is its performance efficiency?
- Assembly tasks (time in seconds; immediate predecessors): A 5 (–), B 3 (A), C 4 (A), D 6 (B), E 2 (C), F 5 (D, E). Using the ranked…
- Two stages are in series. Stage 1 scraps 10% of what it processes, and Stage 2 scraps 5% of what it receives. Scrapped units are not…
- Patients arrive at 20 per hour. 60% go to station X (3 nurses, 12 minutes each), 40% go to station Y (3 doctors, 18 minutes each), and…
- At a single-server counter (M/M/1), customers arrive at 15 per hour and are served at 20 per hour. What fraction of arriving customers…
- A call centre receives 20 calls an hour, and each call takes an average of 6 minutes. What is the smallest number of agents for which the…