A project has a single critical path of 20 days and no other path longer than 12 days. Indirect costs are ₹5,000 a day. Activities on the path can be crashed: P at ₹3,000/day (up to 2 days), Q at ₹4,500/day (up to 2 days), R at ₹6,000/day (up to 3 days). What duration minimises total project cost?

  1. A. 16 days
  2. B. 18 days
  3. C. 13 days
  4. D. 20 days

Correct answer: A. 16 days

Crash a day only while its cost is below the ₹5,000 daily saving: P (2 days) and Q (2 days) qualify, R does not. Duration = 20 − 4 = 16 days, saving ₹20,000 − ₹15,000 = ₹5,000. Crashing R as well (13 days) costs more than it saves.