A project has a single critical path of 20 days and no other path longer than 12 days. Indirect costs are ₹5,000 a day. Activities on the path can be crashed: P at ₹3,000/day (up to 2 days), Q at ₹4,500/day (up to 2 days), R at ₹6,000/day (up to 3 days). What duration minimises total project cost?
- A. 16 days
- B. 18 days
- C. 13 days
- D. 20 days
Correct answer: A. 16 days
Crash a day only while its cost is below the ₹5,000 daily saving: P (2 days) and Q (2 days) qualify, R does not. Duration = 20 − 4 = 16 days, saving ₹20,000 − ₹15,000 = ₹5,000. Crashing R as well (13 days) costs more than it saves.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- Maximise Z = 4x + 3y subject to 2x + y ≤ 20, x + 3y ≤ 30, x ≤ 8, x, y ≥ 0. What is the optimal value of Z, and which constraint is not…
- Maximise Z = 4x + 5y subject to x + y ≤ 8, x + 3y ≤ 18, x, y ≥ 0. The optimum is x = 3, y = 5. Keeping everything else fixed, over what…
- A refinery makes products A (x litres) and B (y litres). Management insists that A must be at least 30% of total output. Which linear…
- In the optimal LP solution of a product-mix problem, product T is not produced and its reduced cost is −₹6 per unit. What does this mean?
- An LP for the number of trucks to buy gives x = 3.6, y = 2.4 at the optimum. Which statement about simply rounding to x = 4, y = 2 is…
- Unit costs (₹) from sources S1, S2, S3 (rows) to destinations D1, D2, D3 (columns): S1: 4, 10, 7; S2: 9, 6, 5; S3: 3, 2, 8. Supplies are…