Four jobs wait at one machine (processing hours; weight = importance): A (4; 1), B (2; 3), C (6; 2), D (3; 3). Using the weighted shortest processing time rule to minimise total weighted completion time, what is the minimum total weighted completion time?

  1. A. 60
  2. B. 48
  3. C. 58
  4. D. 15

Correct answer: C. 58

WSPT orders jobs by processing time ÷ weight: B 0.67, D 1.0, C 3.0, A 4.0. Completion times 2, 5, 11, 15 give 2×3 + 5×3 + 11×2 + 15×1 = 58. Plain SPT (B, D, A, C) gives 60.