Four jobs wait at one machine (processing hours; weight = importance): A (4; 1), B (2; 3), C (6; 2), D (3; 3). Using the weighted shortest processing time rule to minimise total weighted completion time, what is the minimum total weighted completion time?
- A. 60
- B. 48
- C. 58
- D. 15
Correct answer: C. 58
WSPT orders jobs by processing time ÷ weight: B 0.67, D 1.0, C 3.0, A 4.0. Completion times 2, 5, 11, 15 give 2×3 + 5×3 + 11×2 + 15×1 = 58. Plain SPT (B, D, A, C) gives 60.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- Seven jobs taking 8, 7, 6, 5, 4, 3 and 2 hours are to be run on three identical parallel machines. Using the longest-processing-time (LPT)…
- A machine has a mean time between failures of 400 hours and a mean time to repair of 20 hours. What is its steady-state availability?
- A pump fails at random (constant failure rate) with a mean time between failures of 400 hours. What is the probability that it runs a…
- A subscriber yields a margin of ₹600 a year, paid at the end of each year he stays. The annual retention rate is 80% and the discount rate…
- Acquiring a customer costs ₹3,000. Each customer pays ₹500 a month at a 60% gross margin and is retained throughout. Ignoring discounting…
- When a product's price rose from ₹100 to ₹120, monthly sales fell from 1,000 to 850 units. What is the arc (midpoint) price elasticity of…