Management & CommerceHardOps MT · MBA placement
Activities A (4 days) and B (6 days) can start at once and run in parallel, and C (3 days) can start only when both are done. A and B each need the site's only crane for their whole duration. What is the shortest project duration?
- A. 9 days
- B. 10 days
- C. 13 days
- D. 16 days
Correct answer: C. 13 days
Without the resource limit the duration would be max(4, 6) + 3 = 9 days. With one crane, A and B must run one after the other (10 days), and C follows: 13 days. Resource constraints can lengthen a schedule beyond its critical path.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- A firm has ₹10 crore to invest and four indivisible projects (cost; NPV, ₹ crore): P1 (5; 8), P2 (4; 6), P3 (3; 5), P4 (6; 9). Which…
- A decision-maker's utility for wealth x (₹ lakh) is u(x) = √x. She is offered a venture paying ₹100 lakh with probability 0.5 and nothing…
- In a survey of 400 customers, 120 say they would pay for express delivery. What is the 95% confidence interval for the true proportion?
- In acceptance sampling, a good lot (at the acceptable quality level) is rejected by the sampling plan. What kind of error is this, and who…
- Using 30 observations, Model A has 2 predictors and R² = 0.70; Model B has 6 predictors and R² = 0.73. Which statement is correct?
- A logistic regression of loan default on a 'missed a payment last year' dummy gives a coefficient of 0.7. Holding other variables fixed…