Activities A (4 days) and B (6 days) can start at once and run in parallel, and C (3 days) can start only when both are done. A and B each need the site's only crane for their whole duration. What is the shortest project duration?

  1. A. 9 days
  2. B. 10 days
  3. C. 13 days
  4. D. 16 days

Correct answer: C. 13 days

Without the resource limit the duration would be max(4, 6) + 3 = 9 days. With one crane, A and B must run one after the other (10 days), and C follows: 13 days. Resource constraints can lengthen a schedule beyond its critical path.