Management & CommerceModerateOps MT · MBA placement

In SMED (single-minute exchange of die), what is the key first step to reduce setup time?

  1. A. Run larger batches so that setups happen less often and cost less per unit
  2. B. Buy a second machine so one can run while the other is being set up
  3. C. Schedule all setups for the night shift so daytime output is protected
  4. D. Split internal from external setup and move internal steps to external

Correct answer: D. Split internal from external setup and move internal steps to external

SMED first identifies which setup tasks truly need the machine stopped, moves the rest to be done while the previous job is still running, and then streamlines what remains. Larger batches hide setup cost rather than reducing it.

More Operations, Supply Chain & Business Analytics questions

Exams that ask this topic