Management & CommerceVery hardOps MT · MBA placement
Jobs arrive at an M/M/1 workstation at 10 per hour. Waiting (in the system) costs ₹100 per job per hour, and service capacity costs ₹40 per hour for each unit of service rate μ (jobs/hour). Total hourly cost = 40μ + 100L, with L = λ/(μ − λ). What service rate minimises total cost?
- A. 12.5 jobs per hour
- B. 20 jobs per hour
- C. 15 jobs per hour
- D. 25 jobs per hour
Correct answer: C. 15 jobs per hour
d/dμ [40μ + 100 × 10/(μ − 10)] = 40 − 1,000/(μ − 10)² = 0, so (μ − 10)² = 25 and μ = 15. Total cost there is 600 + 200 = ₹800/hour; at μ = 20 it is 800 + 100 = ₹900.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- Which statement correctly distinguishes the cycle-service level from the fill rate?
- A one-person repair shop treats jobs on a first-come basis. Its owner proposes giving priority to short jobs (shortest processing time…
- An e-commerce firm's monthly data – Jan: 10,000 orders, revenue ₹50 lakh, marketing spend ₹10 lakh, 2,000 new customers; Feb: 12,000…
- An e-commerce firm's monthly data – Jan: 10,000 orders, revenue ₹50 lakh, marketing spend ₹10 lakh, 2,000 new customers; Feb: 12,000…
- An e-commerce firm's monthly data – Jan: 10,000 orders, revenue ₹50 lakh, marketing spend ₹10 lakh, 2,000 new customers; Feb: 12,000…
- A warehouse receives 1,200 pallets a day and pallets stay an average of 2.5 days. Its racking holds 3,600 pallets. If inbound volume stays…