Jobs arrive at an M/M/1 workstation at 10 per hour. Waiting (in the system) costs ₹100 per job per hour, and service capacity costs ₹40 per hour for each unit of service rate μ (jobs/hour). Total hourly cost = 40μ + 100L, with L = λ/(μ − λ). What service rate minimises total cost?

  1. A. 12.5 jobs per hour
  2. B. 20 jobs per hour
  3. C. 15 jobs per hour
  4. D. 25 jobs per hour

Correct answer: C. 15 jobs per hour

d/dμ [40μ + 100 × 10/(μ − 10)] = 40 − 1,000/(μ − 10)² = 0, so (μ − 10)² = 25 and μ = 15. Total cost there is 600 + 200 = ₹800/hour; at μ = 20 it is 800 + 100 = ₹900.