Management & CommerceHardOps MT · MBA placement

A one-person repair shop treats jobs on a first-come basis. Its owner proposes giving priority to short jobs (shortest processing time first), keeping the same total capacity. What happens to the average number of jobs waiting?

  1. A. It falls, as SPT cuts mean flow time and so, by Little's law, WIP
  2. B. It is unchanged, because total capacity and workload stay the same
  3. C. It rises, because long jobs now wait much longer behind short ones
  4. D. It falls only if fewer jobs arrive, since capacity is unchanged

Correct answer: A. It falls, as SPT cuts mean flow time and so, by Little's law, WIP

With the same work, finishing short jobs first reduces the average completion time and, by Little's law, the average number in the system. Long jobs do wait longer, which is the fairness cost of SPT.

More Operations, Supply Chain & Business Analytics questions

Exams that ask this topic