Management & CommerceModerateOps MT · MBA placement

At a project review, earned value is ₹40 lakh, planned value ₹50 lakh and actual cost ₹35 lakh. Which statement is correct?

  1. A. The project is behind schedule but under budget
  2. B. The project is ahead of schedule and under budget
  3. C. The project is behind schedule and over budget
  4. D. The project is ahead of schedule but over budget

Correct answer: A. The project is behind schedule but under budget

Schedule variance = EV − PV = −10 (behind; SPI 0.8). Cost variance = EV − AC = +5 (under budget; CPI ≈ 1.14). Comparing AC with PV says nothing about efficiency – that is the usual trap.

More Operations, Supply Chain & Business Analytics questions

Exams that ask this topic