At a project review, earned value is ₹40 lakh, planned value ₹50 lakh and actual cost ₹35 lakh. Which statement is correct?
- A. The project is behind schedule but under budget
- B. The project is ahead of schedule and under budget
- C. The project is behind schedule and over budget
- D. The project is ahead of schedule but over budget
Correct answer: A. The project is behind schedule but under budget
Schedule variance = EV − PV = −10 (behind; SPI 0.8). Cost variance = EV − AC = +5 (under budget; CPI ≈ 1.14). Comparing AC with PV says nothing about efficiency – that is the usual trap.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- A maximisation LP has 3 '≤' constraints and 4 decision variables. After adding slack variables, how many variables are basic in any basic…
- A resource's shadow price in an LP is ₹12 per hour, valid for right-hand-side values between 80 and 140 hours; the current availability is…
- For a decision, the expected value of perfect information is ₹18 lakh and the expected value of the sample information from a proposed…
- A supplier's lead time is uniformly distributed between 4 and 10 days. What is the probability that a given order takes more than 8 days…
- What do =MROUND(37, 5), =CEILING(37, 5) and =FLOOR(37, 5) return in Excel?
- 1 March 2026 is a Sunday. What does =WEEKDAY(DATE(2026,3,1)) + WEEKDAY(DATE(2026,3,1), 2) return?